Salem Presbytery Office Building Closure Status
The Presbytery staff continues to be guests of the Clemmons Presbyterian
Church while awaiting the repairs to be completed on the Presbytery office. The
mold-killing agent has been applied to the affected areas. The sheetrock will be
replaced and repainted. Afterwards the carpet in the affected areas will be
steam cleaned, and 48 hours later several air samples will be conducted in the
building to give us a baseline level as to our air quality. If those tests
indicate a safe atmosphere, then all of the carpet in the building will be steam
cleaned and the heating and ventilation ducts will be cleaned of dust and
sterilized. An ultraviolet lamp system will be installed in the heating/air
conditioning air handlers to eliminate bacteria/mold/airborne particles from
henceforth. After this is completed, another air sample test will be conducted
in several of the rooms to indicate the air is safe and no other significant
mold spores exist within the building. Then comes moving day! We’d be glad to
have volunteer help to move some of our furniture around. My appreciation goes
out to the staff for the hardships they have endured as they have continued to
do their job in a professional and caring way. We appreciate your prayers and
look forward to a safe and healthy return. – Sam Marshall |
||
![]() | ||